| CustomerId | Rate | company_name | SRNO | Item_name | Type | Make | Model | SrNo1 | IdNo | CalibrationDate | CalibrationDueDate | CertificateNo | JobNo | CalibratedBy | approvedBy |
| 2594 | 0.00 | Townshine Realities Private Limited | 3 | Concrete Cube | | | | | T-11,2nd Slab Pour-1,Slab Casting | 20 Jan 2026 | | ST251224-3-009 | ST251224-3 | PritiSonavane | Ajay Mhatle |
| 2594 | 0.00 | Townshine Realities Private Limited | 7 | Concrete Cube | | | | | T-4,7th Slab P-1 Pourstrip | 20 Jan 2026 | | ST251224-6-004 | ST251224-6 | PritiSonavane | Ajay Mhatle |
| 1996 | | AG CONSTRUCTIONS | 11 | Concrete Cube | | | | | 17th Slab above 2nd Part SW3,2nd Stage & Column C-2,Fire Lift Stater,Basement Jacketing Column | 20 Jan 2026 | | ST251225-16-002 | ST251225-16 | PritiSonavane | Ajay Mhatle |
| 1270 | 0.00 | Sharad Shree Enterprises | 15 | Concrete Cube | | | | | Tower E3-13th Slab,M40FF | 20 Jan 2026 | | ST251225-19-018 | ST251225-19 | PritiSonavane | Ajay Mhatle |
| 2720 | 0.00 | Nivasa Buildcon | 19 | Concrete Cube | | | | | B Wing 6th Slab | 19 Jan 2026 | | ST251226-5-004 | ST251226-5 | PritiSonavane | Ajay Mhatle |
| 3037 | 0.00 | Arham Realty | 23 | Concrete Cube | | | | | Footing | 21 Jan 2026 | | ST251226-15-002 | ST251226-15 | PritiSonavane | Ajay Mhatle |
| 1863 | | Kate Moze Associates | 27 | Concrete Cube | | | | | E2 Bldg Ftg of colm SW118,113,108,111,106,101 & E1 Bldg Colm From 2nd to 3rd SL SW 28,30 | 23 Jan 2026 | | ST251227-5-006 | ST251227-5 | PritiSonavane | Ajay Mhatle |
| 1863 | | Kate Moze Associates | 31 | Concrete Cube | | | | | E1 Bldg Column from 2nd to 3rd Level SW 24,31 | 21 Jan 2026 | | ST251227-5-014 | ST251227-5 | PritiSonavane | Ajay Mhatle |
| 471 | 0.00 | Invental Projects & Construction | 2 | Concrete Cube | | | | | B Building 10th Slab pour-2 above column casting SW111,115,C20,21,22,13,16 | 19 Jan 2026 | | ST251223-3-022 | ST251223-3 | PritiSonavane | Ajay Mhatle |
| 2594 | 0.00 | Townshine Realities Private Limited | 6 | Concrete Cube | | | | | T-4,8th Slab P-2 Aluform,M45FF | 19 Jan 2026 | | ST251224-6-002 | ST251224-6 | PritiSonavane | Ajay Mhatle |
| 2720 | 0.00 | Nivasa Buildcon | 10 | Concrete Cube | | | | | C Wing 6th to 7th Slab Column | 20 Jan 2026 | | ST251225-8-004 | ST251225-8 | PritiSonavane | Ajay Mhatle |
| 1270 | 0.00 | Sharad Shree Enterprises | 14 | Concrete Cube | | | | | Tower E3-13th Slab,M40FF | 20 Jan 2026 | | ST251225-19-017 | ST251225-19 | PritiSonavane | Ajay Mhatle |
| 2720 | 0.00 | Nivasa Buildcon | 18 | Concrete Cube | | | | | A Wing Foundation Raft | 23 Jan 2026 | | ST251226-5-002 | ST251226-5 | PritiSonavane | Ajay Mhatle |
| 23597 | 0.00 | Someshwar Infra LLP | 22 | Concrete Cube | | | | | Retaining Wall | 18 Jan 2026 | | ST251226-12-003 | ST251226-12 | PritiSonavane | Ajay Mhatle |
| 1863 | | Kate Moze Associates | 26 | Concrete Cube | | | | | E1 Bldg Column From 2nd to 3rd Slab Level SW33,39,45 | 22 Jan 2026 | | ST251227-5-004 | ST251227-5 | PritiSonavane | Ajay Mhatle |
|